I. Mahallah At-Tabari
Ventilation problem and solution
1. To change fix panel window glass to air lourves and add ventilation fan for each room.
- 2 months to complete (From 21st June 2011 until 20th August 2011)
2. To provide partition for all rooms for privacy but will reduce the no of occupant of 2 for each room.
- 2 months to complete (From 21st June 2011 until 20th August 2011)
3. To provide table light for all.
- 2 weeks to complete. (From 6th August 2011 until 20th August 2011)
4. Cloth hanger room for all blocks.
- 1 month (From 22nd July 2011 until 20th August 2011)
5. To setup a fellow, principal and TV room.
- 1 month to complete. (From 22nd July 2011 until 20th August 2011)
Overall renovation works date is from 21st June until 20th August 2011
_________________________________________________________________________
II. Mahallah IM-2
Ventilation problem at ground level and solution
1. To scrap off the suspended ceiling (increase height) for allowing the ventilation flow.
- 1 month (From 21st June 2011 until 21st July 2011)
2. Rewiring for additional ceiling fan and extractor fan.
- 2 months to complete (From 21st June 2011 until 20th August 2011)
Overall renovation works date is from 21st June until 20th August 2011
________________________________________________________________________
III. Facilities for the disabled students at Gombak campus
1. Upgrading of disabled toilet at Mahallah Uthman
- Status: completed
2. To construct concrete ramp near the bridge connecting Kulliyah of Economic and Kulliyah of Law
- 14 days to complete
Construction date is from 13th June until 27th June 2011
Thank you, wassalam.
Ir. Shaffei bin Mohamad
Director
Development Division
Level 1, Rectory Building
International Islamic University Malaysia
Jalan Gombak
53100 Kuala Lumpur